FOLLOWING ANNOUNCEMENTS made on Monday 1st Aug 2011 that Redhall Engineering was claiming a victory in the ongoing contractual dispute at the Saltend bio-ethanol construction site, Vivergo has now hit back with a counter claim that the same adjudicator had found that Redhall was in "material breach" of its contract.

Vivergo Fuels has said it stands by the decision to terminate its contract with Redhall Engineering and disputes any claim for damages for up to £16.7m but accepts that it failed to give Redhall adequate notice of  its termination of contract.

In a statement yesterday published on TheBusinessDesk.Com, Vivergo said "We welcome the finding of the adjudicator that confirms that Redhall was in material breach of the contract, and are disappointed that, in the adjudicator’s opinion, we failed to give the correct notice."

0 comments:

Post a Comment

Comments

About This Blog

Just might be of interest to those active in HU12 (post code area) communities and partnerships!?

Sitemeter

Blog Archive

Admin

Hedon Blog

  © Blogger templates The Professional Template by Ourblogtemplates.com 2008

Back to TOP